Attala & Webster County Fiber Expansion

Attala & Webster Counties, Mississippi

Hometown Connections, Made Stronger

Fiber internet is coming to Attala and Webster counties through the BEAD Program, backed by people-first support from your neighbors at Arriva.

See Our Progress Register Your Interest Fourth-Generation Family-Owned 100+ Years in the Industry $38.5 Million BEAD Investment What is BEAD Why Fiber Reviews Map & Register About Arriva Events FAQs

Construction is happening in phases. Scroll down to see the build map and timeline for your area.

The BEAD Project

What is BEAD?

Building World-Class Connections for Mississippi

The Broadband Equity, Access, and Deployment (BEAD) Program is a $42.45 billion federal grant initiative designed to expand high-speed internet access and bridge the digital divide across all 56 U.S. states and territories. Our goal at Arriva is to serve rural America, and the BEAD project helps support that. Fiber optic broadband is now a foundational driver for modern rural society, and will position Webster and Attala Counties, as well as the state of Mississippi, for continued economic growth. Arriva is proud to support a $38.5M BEAD grant with matching private funds to extend our fiber network, providing you with stronger access for work, learning, healthcare, and everyday life.

$38.5M BEAD investment 535+ Miles of new fiber 3,100+ Homes & businesses reached 100% Fiber to the home Why Fiber

Only the Best for Our Neighbors

Ridiculously Reliable

Get the fastest speeds around, with no interruptions due to distance, number of devices, or neighborhood demand. Plus, our buried cable means fewer weather related outages.

Transparent Pricing

No introductory rates, overage fees, or hidden fees, period.

Fast and Unlimited

Game, stream, and browse all you want, with no limit to devices. No data caps, no throttling, no headache.

Local Support

From a family-run business that cares about our community, and wants you to love your service.

Reviews

Here’s What Your Neighbors Are Saying

From Arriva customers in Bruce, Mississippi, the nearest Arriva-served community to this build area.

“Super nice ladies in the office always in a great mood! I look forward to my next visit.”

Chad G., Bruce, Mississippi

“Speedy service, fastest internet I’ve ever had! Go with these guys!”

Veronica F., Bruce, Mississippi

“The Bruce Arriva group are the best to work with. They were able to help us extend our Wi-Fi to our workshop. All the employees are friendly, knowledgeable, and willing to help at all times.”

Deb B., Bruce, Mississippi

“Great customer service, great service and an outstanding crew that works for them.”

Thomas S., Bruce, Mississippi

Coverage & Registration

Where We’re Building

Fiber construction across Attala and Webster counties is happening in phases. Use the map below to see where things stand near you, then register your interest so we can reach out the moment fiber is ready at your address.

Fiber Internet Available

Great news, lightspeed fiber internet is here in your area. Enter your address to see if internet is available at your home.

Under Construction

Our crews are actively working to bring fiber to your home. Register today to get notified as soon as it’s available.

Coming Soon

We are still in the planning and engineering stages to bring our 100% fiber network to you. Register your interest to be the first to know when we get started.

Register Your Interest

Register your interest to receive timely updates on our build, and to be among the first to know when fiber is ready at your address. There’s no cost or obligation to get service through us.

Sign Me Up

The Road Ahead: Six Phases of Construction

Building 535+ miles of fiber takes more than construction. Here is the current phase-by-phase plan across the project area. Dates below are estimates and may change.

Phase Route Est. Construction Timeline Fiber Built Customer Installs
1 Bruce to Eupora via Hwys 9 & 82 Feb. 2027, Sept. 2027 92 miles Sept. 2027
2 Possumneck, Hesterville, NW of Kosciusko from Hwy 82 July, Dec. 2027 75 miles Dec. 2027
3 N of Kosciusko toward French Camp July, Dec. 2027 95 miles Jan. 2028
4 Downtown Kosciusko, Durant, Sallis, McAdams, Zemuly Oct. 2027, Aug. 2028 142 miles July 2028
5 SE Kosciusko to County Line Road Nov. 2027, Mar. 2028 58 miles July 2028
6 E of Kosciusko, including Williamsville, Ethel, McCool Jan., Aug. 2028 74 miles Aug. 2028

Dates are estimates and subject to change.

Installation Process

What to Expect During Construction

Construction happens in two stages. First, the mainline build along the highways, which is the backbone that will support every home and business in that stretch. Once that’s done, the edge-out work that brings fiber to individual homes begins.

  1. Highway Mainline Construction

    Crews lay the main fiber line along the highway corridors shown in the construction timeline above. This backbone has to be in place before any individual home in that phase can be connected. Ali is sending more specific detail on this step, so check back for an update here.

  2. Locating Utilities

    Our crews and local utility companies will mark their lines in your yard using spray paint, colored flags, or other markers.

  3. Street-Level Fiber Construction

    Contractors will place the fiber-optic cable in the ground on your street, then splice the fiber to the pedestal near your home.

  4. Fiber Drop

    Workers will bury a fiber line to your home, then install a fiber box on the side of your house to prepare for installation, for those who are registered.

  5. Installation

    Arriva will call you to schedule your installation appointment. On the day of installation, an Arriva technician will hook up your internet and make sure everything is working smoothly.

  6. Celebrate

    That’s it, enjoy your new, high-speed internet connection.

What It Takes to Keep Us Moving

Required at various stages:

  • Engineering and design approvals and modifications
  • Permitting
  • Environmental review and clearance
  • Agreements and contracts
  • Quality control inspections
  • BEAD program approvals

Variables we try to plan around:

  • Weather
  • Contractor schedules
  • Material shortages and delays
  • Field conditions
About Arriva

Making It Easier for People to Connect

Since we got our start in 1923, that’s been our goal. First, with local phone lines, and now, with the gold standard of internet technology: fiber internet. When you choose us, you’re choosing a family-run company with more than a century of dedication to our Mississippi neighbors. Our investment in fiber is about more than making it easy for you to stream your favorite shows. It’s about strengthening the community, opening new opportunities, and building a future-proof network that will meet your needs for decades to come.

Read Our Full Story

A Mississippi Company at a Glance

  • Fourth-generation, family-owned Mississippi telecommunications company
  • Serving rural communities since 1923
  • More than $28 million invested in fiber since 2015
  • 24,000+ homes and businesses passed by fiber construction to date
  • Nearly 80% of Arriva customers already served with fiber

Our Core Values

Tradition with Innovation

Blending heritage and values with forward-thinking approaches to drive progress.

Outstanding Customer Care

Providing exceptional support and tailored solutions for every customer.

Fairness & Integrity

Upholding ethics and transparency, fostering trust and equity in all endeavors.

Team & Community

Cultivating community engagement, enriching lives beyond business.

Events

You’re Invited

Join us at an open house or meet and greet near you, where we’ll answer questions and share more about the fiber build in your area. These events are open to all, no RSVP necessary.

Recap

Webster County Board of Supervisors Presentation & Informational Session

Date: September 30, 2026
Time: 8:30 a.m.
Location: Webster County Courthouse

Thank you to everyone who joined us. We shared project details and answered questions about the fiber build coming to Webster County.

Common Questions

Frequently Asked Questions

We’re sure you have them, so here are some answers to the most common ones.

What is fiber?

Fiber internet uses pulses of light to deliver data through glass tubes, rather than traditional copper (DSL) or coax (cable) cables.

Why is fiber better than other internet options?

Since light is not affected by distance, fiber provides faster speeds, more reliability, and better performance than traditional cable or DSL connections, which can be slowed by distance and signal strength, even during peak times.

Who is Arriva?

We’re a family-owned company focused on delivering high-quality broadband and communication services to communities through long-term investment and local support.

When will fiber be available in my area?

Service will be rolled out in phases. Check the construction map above to see if your area is under construction, coming soon, or already available.

How do I sign up for service?

You can register your interest online using the button above, or contact us directly. Once service is available in your area, we’ll guide you through the next steps.

How will I know when construction is getting started near me?

We’ll leave a door tag on your home to let you know we’ll be in the area.

How do I prepare for construction on my property?

As we get close to digging near individual homes, it helps us to know about any invisible fences, underground gas lines or tanks, landscape lighting, French drains, and similar features. To share this information, contact us at 662-983-4343. Our goal is to ensure a smooth construction process for all residents, and knowing this information helps us work around these details.

What are those lines or flags in my neighborhood?

Before construction begins, our crews mark utility lines before digging. This process is a mandated state requirement, and Arriva follows all applicable laws and guidelines. Locating existing underground utility lines prevents those lines from being accidentally damaged during construction of the new fiber-optic network. This process, called locating, involves spraying temporary paint on grass or hard surfaces to indicate where the fiber network will potentially go. Once this step is complete, other utilities in the area, like power, water, and telecommunications, will follow the lines within the neighborhood to locate their own utilities and prevent service impacts or damage during digging.

Small Town Doesn’t Mean Small Potential